Project Timeline
With planning permission secured, we’re now moving into the delivery phase of the project. The timeline below outlines the key stages in transforming 110 The Queen’s Walk into a modern, sustainable and vibrant destination.
Programme
Enabling works – August 2025 to February 2026
Hoardings installed from 11 August
Scaffolding for façade removal
Basement foundation and drainage upgrades
Site welfare, hoists and services installed
Environmental monitoring and recycling of glazed cladding
Main construction works – February 2026 to Summer 2028
Full refurbishment of all floors and below-ground space
New green terraces and enhanced public realm
Fit-out of office, retail and restaurant spaces